MARIPOSANS FOR THE ENVIRONMENT AND 
RESPONSIBLE GOVERNMENT MARIPOSANS FOR THE ENVIRONMENT AND MARIPOSANS FOR THE ENVIRONMENT AND
 

 

Contact Us

MARIPOSANS FOR THE
ENVIRONMENT AND
RESPONSIBLE GOVERNMENT
P.O. Box 2121
Mariposa, CA 95338
info@merg-mariposa.org

MARIPOSANS FOR THE ENVIRONMENT AND

 

Embankment Dam Studies

 

 A paper by Robert B. Jansen, consulting civil engineer (former chairman of USCOLD (now US Society on Dams) and director of design and construction for the USBR and the California Department of Water Resources) on “Dangers at Embankment Dam Boundaries and Embedments,” discusses the variety of issues that might be experienced by an embankment dam built circa Exchequer Dam in the mid-1960s.  Mr. Jansen is a member of the National Academy of Engineering, and he has authored and edited books on dams, including Advanced Dam Engineering and Dams and Public Safety.

 

 “Significant numbers of embankment dams have failed from either external or internal attack. The threat of inevitable floods and earthquakes, which give few useful signs of their approach, is different from that of the already-present but unseen – and often more immediately dangerous – flaws within a dam and its foundation.

 

“Embankments differ from other dams in their composition of deformable natural materials that are largely inaccessible once embodied in the fill. Behaviour of earth and rockfill zones will be more predictable if they are free of penetrations or other encumbrances. Facilities located upon, against, or inside the dam body add to uncertainties and thereby to the possible modes of failure. Dam engineering requires reducing unknowns to a minimum.

 

 “The long history of earthfills and rockfills shows that many of their problems were spawned by designers through inadequate safeguarding of embankment boundaries and introduction of unreliable components into the hearts of the dams. Vulnerability may be found at internal zone limits, foundation contacts, structural faces, or works buried in the fill. An embankment should be zoned for internal stability and capable of conforming naturally to its site without appurtenances or foundation characteristics that might hamper its behaviour.”

 

 His paper points to early issues at Exchequer Dam:

 

 “Damaging settlement and cracking has occurred at concrete facings on rockfill dams built before the 1970s by dumping and sluicing in high lifts. More recent rockfills compacted by vibratory rollers and given improved zoning and face slab and plinth details have performed much better. Methods for repair of faces on the early dams have evolved from concrete patching to filling of cracks with expansive mortar, mastic, or clay-bentonite slurry to rubber, shotcrete, or synthetic membrane overlays….

 

 “Some embankments built in the 20th Century as replacements for old dams incorporate parts of the earlier works. The design of California ’s 490ft high (149m) New Exchequer Dam, a concrete-faced rockfill constructed in 1964-66, used its predecessor, a 326-ft-high (99m) gravity dam, as the upstream toe block. An ineffective flexible asphalt-impregnated joint seal was provided where the slab met the downstream face of the old dam 185ft (56m) above its base. Settlement of the rockfill caused severe separation and spalling of slab joints and leakage reaching a maximum of about 490cfs (14m3/sec) in 1967. Repairs in that year were concentrated on sealing the opened joint between the two dams by underwater placement of bentonite-enriched earthfill. This was effective with later replenishment of lost material and addition of a geotextile blanket reducing total leakage by 99%. However, as the dam continued to settle, other face joints needed remedial work, which has included concrete filling, new flexible waterstops, and membrane covering.”

 

 Mr. Jansen addresses the issue of remediating inadequate spillways, such as would be created by raising the crest level of Lake McClure, which, therefore, necessitates MID’s Spillway modification project.

 

 “When spillways for embankment dams are inadequate, safe and economical remedial alternatives may be limited. If the present facilities cannot be enlarged, the additional capacity preferably should be developed by works located away from the dam. At some projects, however, embankments have been armoured for overtopping. This previously objectionable practice has won some endorsement for infrequent discharges over lesser dams, partly because of the increased quality of roller compacted concrete. The safety of overlays for higher embankments remains unproven. Caution is required in evaluating the possible effects of high velocities, overflowing debris, settlement, cracks, underseepage and uplift, and sliding on slopes. Armour must have underdrains that are kept clean by effective filters. Protection must also be provided against erosion of the dam at the overlay edges and in the approach area of the embankment slope immediately upstream. Safe dissipation of the discharge energy at the toe of the dam would be imperative if this kind of design is pursued for large structures.”

 

 It is unclear in our research as to whether the toe of Exchequer Dam has been engineered for the additional 183 billion lbs of water weight and pressure that the increase in crest elevation would permit.

 

 Mr. Janson’s paper discusses new science with regard to use of geosynthetics to halt seepage, and the potential for lack of durability of such retrofits:

 

 “Flexible synthetic sheets have been used increasingly in embankments for seepage control. In dams typically intended to last hundreds of years, the durability and service life of these embedded manufactured products are of principal concern. Survival depends on the materials, the manner of placement, the function of the installation (e.g., zone divider, filter, drain, reinforcement), and the effects of embankment deformation and cracking. Geosynthetics implanted in an earthfill become integral parts of the dam, usually without access for inspection or ready repair. They must be resistant to the various forces and processes that cause their deterioration. Clogging of filters and drains may reduce their effectiveness to intolerable levels.

 

 “Internal geosynthetics constitute discontinuities that may have lower shearing resistance than the neighboring zones of natural materials. Some multilayered systems may undergo differential slipping of the sheets. Synthetics can fail if their junctions with the dam foundation are deficient. Hydraulic gradients at that contact are high, so leakage could escape at damaging velocities.

 

 “Use of synthetics as permanent members in an embankment’s zoning has been under way for little more than thirty years and, while much has been learned, the relatively short experience has not resolved all questions as to dependability and durability. Embedment of geotextiles as internal filters in big dams is not generally accepted as a satisfactory alternative to well-designed composites of hard sands and gravels, which have been thoroughly proven in long-time service.”

 

 “Synthetics have also been placed on the upstream slopes of embankments, and as liners for reservoirs (e.g., San Joaquin Reservoir, California , 2004). Such elements can be accessible for inspection and repair, during drawdown or by divers, which is an advantage not shared by deeply buried synthetics. Access is also a merit of lightly covered geotextiles in drainage works.”

 

 

Introduction Page – HR869 & HR2578

MERG Current Thoughts on HR 869 & HR 2578

New Exchequer Dam and Lake McClure

FERC Project Boundary Question

The FERC Relicensing Argument

Spillways at Lake McClure

Dam Safety

Embankment Dam Studies

Is Raising the Dam Crest Elevation Unlawful?

Known Geologic Issues

The Effect on the Limestone Salamander

Other Options for Additional Water Storage

MERG Early Thoughts on HR 869