MARIPOSANS FOR THE ENVIRONMENT AND 
RESPONSIBLE GOVERNMENT MARIPOSANS FOR THE ENVIRONMENT AND MARIPOSANS FOR THE ENVIRONMENT AND
 

 

Contact Us

MARIPOSANS FOR THE
ENVIRONMENT AND
RESPONSIBLE GOVERNMENT
P.O. Box 2121
Mariposa, CA 95338
info@merg-mariposa.org

MARIPOSANS FOR THE ENVIRONMENT AND

The FERC Relicensing Argument

 One of MID’s arguments is that HR 869 really does nothing other than to allow FERC to consider the spillway modification project, which it is currently not allowed to do because of existing law, the WSRA.  From Brian Kelley’s testimony before the House Subcommittee:

 

"H.R. 869 does not mandate, authorize or in any way pre-judge the merits of the proposed spillway modification project. It simply allows the project to undergo a rigorous examination by FERC and other Federal and State agencies in a public process that will identify and address all potential impacts in accordance with the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA), the Federal Endangered Species Act ( ESA) and the California Endangered Species Act (CESA). "

 

The problem with this argument is that MID will spend two years doing a CEQA and NEPA, etc. and will submit a single proposal to FERC, the one in their PAD and the one that includes raising the level of the reservoir by 10 ft.  They will want to make very sure before spending the time and money on the various studies and relicensing, that the process will have a positive outcome.

 

 At this same hearing, Representative Garamendi asked Denham if he would consider modifying his proposed bill to simply allow FERC to consider the proposal without actually amending (in effect) the WSRA.  Then, he suggested, when all of the other relevant issues were known, Congress could decide whether the situation warranted changing the WSRA, something he suggested should only be considered under the most extreme circumstances. 

 

 Denham deferred to Kelley who said basically that MID would not spend the time and money on a relicensing process unless they had reasonable assurance that there would be no legal impediment to its completion.  He dismissed the proposal as unworkable.

 

 That is the problem for us with MID’s argument.  If the WSRA was removed as an obstacle and HR 869 would have the force of law, it would be a powerful bargaining chip in the negotiations, and there would likely be no legal reason for FERC to refuse raising the reservoir.  Who knows whether engineers would have a public safety problem with the issues described below or someone would find a Native American sacred site in the way?  Will Salamanders rule the day?  Don’t think so. 

 

 The likely effect of allowing the WSRA to be breached is that the Merced Wild and Scenic River would be ravaged in fact as well as by law. 

 

Introduction Page – HR869 & HR2578

MERG Current Thoughts on HR 869 & HR 2578

New Exchequer Dam and Lake McClure

FERC Project Boundary Question

The FERC Relicensing Argument

Spillways at Lake McClure

Dam Safety

Embankment Dam Studies

Is Raising the Dam Crest Elevation Unlawful?

Known Geologic Issues

The Effect on the Limestone Salamander

Other Options for Additional Water Storage

MERG Early Thoughts on HR 869