Early
Thoughts on HR 869 – The First Bill Introduced by Congressman Denham
HR 869 is an amendment to Public Law 102-432, the
bill, signed into law by George W. Bush amends the WSRA to include the
lower
The language
in HR 869 itself is interesting. It
says:
A
To clarify the definition of
flood control operations for the purposes of the operation and maintenance of
Project No. 2179 on the
Be it enacted by the Senate and House of Representatives of
the
SECTION 1. FLOOD CONTROL OPERATIONS CLARIFIED.
Section 3 of Public Law 102–432
is amended by adding at the end the following: ‘‘For purposes of this section,
‘flood control operations’ shall include occasional short- term increases in
the level of Lake McClure not to exceed elevation 877 feet mean sea level for a
period not to exceed 60 days between May 1 and July 31 of above-normal water
years, as defined by the San Joaquin Valley 60–2 20–20 Hydrological
Classification Index, developed by the California State Water Resources Control
Board, or any successor index applicable to the Merced River water-shed.’”
HR 869 does not say: For the purpose of providing more water
for homes and agriculture, as well as clean energy….
HR 869 does not say: For the purpose of protecting life and
property in
Flood Control Operations
Normally flood control operations for a dam and
reservoir are determined by flood control curves
or rule curves that define the maximum allowable reservoir pool elevation and
therefore water storage as a function of day and month as can be seen in the
diagram below.
![]() |
These rule curves are imposed by the
From the PAD MID submitted in 2008:
“Articles
39. This article requires Licensee to enter
into an agreement with the United States Army Corps of Engineers (
To
adhere to these limits, Licensee pre-releases water from
There is obviously a tension between the water
storage limitations imposed by the rule curves and MID’s desire to capture,
store and sell as much water as possible.
HR 869 seemingly seeks to change the definition of
“flood control operations” for the Exchequer Dam and
If this interpretation of HR 869 were implemented,
it would seem questionable in terms of flood control and the ability to
accommodate snowmelt. It is unfortunate that HR 869, on the surface, seems to
specifically authorize an irresponsible operation of the dam and therefore
would seem to threaten public safety.
Another approach to the interpretation of the
effects of HR 869 would be for the FERC relicensing to require rule curves and
conditional space to be imposed by the Corp of Engineers, in this case, based
on a new maximum level of 877, and taking into account the changes in weather
patterns in the future due to climate change, [RCK2]etc. This would be a more responsible approach in
terms of flood control operations and it would likely require seasonal
operating levels in the lake to be at or below current required levels.
It is hard to guess which of these interpretations
MID is intending to use if HR 869 passes.
Clearly MID's Pre-application Document (PAD) in 2008 and study plans in
2009 have been perhaps purposely vague about how they would “re-operate”
"conditional storage". HR 869
would seem to add “clarity”, as it is very specific about storage levels and
time frames. To the extent that HR 869 can be seen as superseding the
In either case, by allowing operation 10 ft above
the current WSRA defined maximum level of 867 ft, HR 869 is in direct conflict
with the WSRA.
Thus HR 869 would seem to violate at least several
fundamental environmental laws, at a minimum the Wild and Scenic Rivers act and
the California Endangered Species Act (see section on the Limestone
Salamander) Therefore it would seem not
likely to get through the congress and the President or the courts. It should
also be noted that all of these issues are discussed in MID’s PAD and dismissed
as not an issue, or an issue that could be resolved by further study.




